Estralin PS has signed the contract for cable and cable accessories delivery of SS “Empalme II” project in Empalme, Mexico. Estralin PS service center carried out cable laying supervision of 400 kV 800 mm2-Al-XLPE-HDPE Cable – 3,7 km and...
The first step of installation works at SS “Bystricany” has finished. Estralin PS service center was responsible for cable laying supervision and cable accessories installation of NKT Cable production.
Estralin PS is carrying out cable delivery A2XS(FL)2Y 800RM/95-64/110 kV-7,7 km of Estralin HVC production. The name of the project is SS «Bystricany», Slovakia.
At the site CL 110 kV SS “Podunajske Biskupice” – SS “Slovnaft”, Slovakia the MKB 126 accessories installation is carried out, the accessories are produced by Arkasil SK. Cable type is A2XS(FL)2Y1х1600RMS/200 64/110 kV – 18,6 km of Estralin...
Our company keeps up with the times and meets the European standards of quality and safety. Recently, our factory was visited by the auditors from ABB, after the meeting we received favorable report with the recommendations on business processes...
At the site CL 110 kV HPP-1-TPP-12 №1, 2 with feeders at SS “Bersenevskaya”-SS “Pavaleckaya” the EHSVS 123 kV accessories installation is carried out, the accessories are produced by Suedkabel. Cable type is 2XS(FL)2Y-LWL 1×1200 RMS/265-64/110 kV and 2XS(FL)2Y-LWL...
Estralin HVC started cable production 2XS(FL)2Y-LWL 1x800RM/185-64/110 kV for SS 110 kV/10 kV “Stadium” construction, Russia, Samara.
Estralin HVC started cable production A2XS(FL) 2Y 1x1600RMS/100-64/110 kV-7,7 km. The project name is SS “Orion”, Bulgaria.
The contract for cable delivery A2XS (FL) 2Y 1x300RM/120- 64/110 kV -8,6 km of Estralin HVC production and cable accessories MКВ-126-12 pcs., MCB-126X-12 pcs. produced by Arkasil SK was signed. The project is CL 110 kV SS “Vladimirskaya”-SS “Yandex...