SS 110 kV “Tuapse-Terminal”, Tuapse, Russia

Estralin HVC has started cable production A2XS(FL)2Y1X500RM/150-110 kV-8,9 km for the second phase of SS 110 kV Tuapse-Terminal construction – which will be laid under the embodiment passing near a highway. The line will be in a special cable collector, it will provide access to operational wells, so open the pavement to service or repair is required. Just ahead of schedule by more than two (2) weeks, with respect to the customer terms of supply, terminations MKB126-AL 500/150 in the amount of twelve (12) pieces and joints MCB 126-AL 500/150 in of 12 (twelve) units of Arkasil SK production were manufactured and shipped to the customer. Installation work will start soon.