The contract for cable delivery 2XS(FL)2Y1x400RM/95-20/35kV-0,8km,2XS(FL)-LWL1x2000RMS/160-64/110kV-1,3km and 2XS(FL)2Y1x1200RMS/160-64/110 kV-1,9 km by Estralin HVC production and for cable accessories delivery by Arkasil SK production and for the service rendering of cable accessories installation for power unit construction of Verkhnetagilskoy Regional...
Estralin HVC has started cable production 2XS(FL)2Y-LWL 1X1200RMS/265-110kV – 36,02 km for CL 110 kV “Hydro-electric power station-1-Heat Power Station 12” reconstruction, Moscow.
The first stage of installation works at the site 110 kV Substation Tuapse-Terminal has been finished. 2 sets of terminations MKB 126 and 2 sets of transposition joints MCB 126 X of “Arkasil SK” production are installed.
The installation works at SS 110 kV Tuapse-Terminal site have started. Cable accessories instalation is made by Estralin PS service center under Arkasil SK supervision. It will be installed 12 terminations MKB 126 and 12 joints transposition MCB 126...
Estralin HVC has started cable production A2XS(FL)-H 1X400RM/265-127/220kV – 2,7km for 4-th power unit reconstruction at Rostov nuclear power station, Volgodonsk, Rostov Region.
The order for the GIS EHSVS-145 Type A production is placed, Suedkabel. Cable laying supervision and cable accessories installation is made by the service center “Estralin PS” for the project SS 110/20 kV project “Airport-Novaya”, Astana (Kazakhstan).
Estralin HVC has started cable production 2XS(FL)2Y1X500RM/100-64/110kV – 43,4km and 2XS(FL)2Y1X1600RMS/200-64/110kV-24,8km for expansion of SS 110/20 kV “Aeroport-novaya”, Astana (Kazakhstan).
Estralin HVC has started cable production A2XS(FL)2Y1X300RM/120-64/110 kV-4,5 km for the grid connection of 110/10 kV substation “Geoport” providing energy Novorossiysk naval base of the Black Sea Fleet. Cable laying and installation works should begin in the near future.
Estralin HVC got a review from Russian High-Voltage Cable Networks, it is a branch of “Moscow United Electric Grid Company”” for fast cable delivery and cable laying of Estralin HVC cables.
Estralin HVC has started cable production A2XS(FL)2Y1X500RM/150-110 kV-8,9 km for the second phase of SS 110 kV Tuapse-Terminal construction – which will be laid under the embodiment passing near a highway. The line will be in a special cable...